<?xml version="1.0" encoding="UTF-8"?><rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	>
<channel>
	<title>Comments on: Project Time Management: Key Tips for Project Success</title>
	<atom:link href="http://www.pm-perspectives.com/project-time-management-key-tips-project-success/feed/" rel="self" type="application/rss+xml" />
	<link>http://www.pm-perspectives.com/project-time-management-key-tips-project-success/</link>
	<description>From One Project Manager to Another</description>
	<pubDate>Tue, 07 Feb 2012 10:24:04 +0000</pubDate>
	<generator>http://wordpress.org/?v=2.7.1</generator>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
		<item>
		<title>By: admin</title>
		<link>http://www.pm-perspectives.com/project-time-management-key-tips-project-success/comment-page-1/#comment-5</link>
		<dc:creator>admin</dc:creator>
		<pubDate>Fri, 23 Jan 2009 00:08:38 +0000</pubDate>
		<guid isPermaLink="false">http://www.pm-perspectives.com/?p=35#comment-5</guid>
		<description>Great Question!

EAC = AC + ETC
Explanation: Estimate at Completion = Actual Cost + Estimate to Complete
Rationale: The project has flawed estimates and there are significant variances. This formula assumes that the project team creates a new ETC forecast from detailed replanning meeting and adds this new estimate of what it will take to finish the project to what the project has already spent. Don’t use this formula if variances are typical as this EAC calculation takes the most project time.

EAC = AC + BAC – EV
Explanation: Estimate at Completion = Actual Cost + Budget at Completion – Earned Value ( e.g., Work actually accomplished)
Rationale: The project variances early in the project are assumed to be atypical variances and will not continue in future periods. This formula only accounts for the over or under spending in the early part of the project and assumes that the spending for the rest of the project will be on-target with the original assumptions.

EAC = (AC + (BAC-EV)/CPI)
Explanation: (Actual Cost + (Budget at Completion – Earned Value)/Cost Performance Index.
Rationale: The project variances early in the project are assumed to be typical variances that will continue in future periods. So the balance of the project spending is adjusted up or down based upon the CPI for the project variances to date. The project manager needs to justify why or why not they believe the original assumptions just need to be adjusted vs. a significant replanning effort begun. The control limits for project spending provides guidance here on what is an acceptable variance vs. what is acceptable. If it is an unacceptable variance, the project needs to use EAC = AC + ETC instead.

EAC = BAC / CPI
Explanation: Budget at Completion/Cost Performance Index.
Rationale: This is a quick and easy formula but it isn’t in the PMBOK. Why? Well, since you are already doing Earned Value Management in a tool or a spreadsheet, some of the other formula’s are more accurate and as easy to calculate. In addition, this formula makes a lot of simplifying assumptions. But it has its’ use as a quick and dirty look that is easily explainable to others. The key question is whether it actually reflects what the future may be. 

Enjoy studying for the PMP or your project adventures!

Rosemary Hossenlopp, PMP

From PMBOK ® Guide Fourth Edition Changes Explained, 2008/05/13 at 3:45 PM</description>
		<content:encoded><![CDATA[<p>Great Question!</p>
<p>EAC = AC + ETC<br />
Explanation: Estimate at Completion = Actual Cost + Estimate to Complete<br />
Rationale: The project has flawed estimates and there are significant variances. This formula assumes that the project team creates a new ETC forecast from detailed replanning meeting and adds this new estimate of what it will take to finish the project to what the project has already spent. Don’t use this formula if variances are typical as this EAC calculation takes the most project time.</p>
<p>EAC = AC + BAC – EV<br />
Explanation: Estimate at Completion = Actual Cost + Budget at Completion – Earned Value ( e.g., Work actually accomplished)<br />
Rationale: The project variances early in the project are assumed to be atypical variances and will not continue in future periods. This formula only accounts for the over or under spending in the early part of the project and assumes that the spending for the rest of the project will be on-target with the original assumptions.</p>
<p>EAC = (AC + (BAC-EV)/CPI)<br />
Explanation: (Actual Cost + (Budget at Completion – Earned Value)/Cost Performance Index.<br />
Rationale: The project variances early in the project are assumed to be typical variances that will continue in future periods. So the balance of the project spending is adjusted up or down based upon the CPI for the project variances to date. The project manager needs to justify why or why not they believe the original assumptions just need to be adjusted vs. a significant replanning effort begun. The control limits for project spending provides guidance here on what is an acceptable variance vs. what is acceptable. If it is an unacceptable variance, the project needs to use EAC = AC + ETC instead.</p>
<p>EAC = BAC / CPI<br />
Explanation: Budget at Completion/Cost Performance Index.<br />
Rationale: This is a quick and easy formula but it isn’t in the PMBOK. Why? Well, since you are already doing Earned Value Management in a tool or a spreadsheet, some of the other formula’s are more accurate and as easy to calculate. In addition, this formula makes a lot of simplifying assumptions. But it has its’ use as a quick and dirty look that is easily explainable to others. The key question is whether it actually reflects what the future may be. </p>
<p>Enjoy studying for the PMP or your project adventures!</p>
<p>Rosemary Hossenlopp, PMP</p>
<p>From PMBOK ® Guide Fourth Edition Changes Explained, 2008/05/13 at 3:45 PM</p>
]]></content:encoded>
	</item>
	<item>
		<title>By: admin</title>
		<link>http://www.pm-perspectives.com/project-time-management-key-tips-project-success/comment-page-1/#comment-4</link>
		<dc:creator>admin</dc:creator>
		<pubDate>Fri, 23 Jan 2009 00:06:41 +0000</pubDate>
		<guid isPermaLink="false">http://www.pm-perspectives.com/?p=35#comment-4</guid>
		<description>EAC=AC+ETC is used if the original estimate of EAC was fundametally flawed and you have to recalculate your estimate (specialy your ETC) all over again.

EAC=AC+(BAC-EV) is used when current variances are considered to be ATYPICAL in the future. We had some problems but it won’t happen again !

EAC=AC+(BAC-EV)/CPI is used when current variances are considered to be TYPICAL in the future. In the future we will continue the same trend of variance as of till now !

EAC=BAC/CPI is the same formula as above… just develop it like EAC = AC + BAC/CPI - EV/CPI and replace EV/CPI by EV/(EV/AC)…

Mike // Jan 11, 2009 at 10:52 pm 
http://www.pmchampion.com/</description>
		<content:encoded><![CDATA[<p>EAC=AC+ETC is used if the original estimate of EAC was fundametally flawed and you have to recalculate your estimate (specialy your ETC) all over again.</p>
<p>EAC=AC+(BAC-EV) is used when current variances are considered to be ATYPICAL in the future. We had some problems but it won’t happen again !</p>
<p>EAC=AC+(BAC-EV)/CPI is used when current variances are considered to be TYPICAL in the future. In the future we will continue the same trend of variance as of till now !</p>
<p>EAC=BAC/CPI is the same formula as above… just develop it like EAC = AC + BAC/CPI - EV/CPI and replace EV/CPI by EV/(EV/AC)…</p>
<p>Mike // Jan 11, 2009 at 10:52 pm<br />
<a href="http://www.pmchampion.com/" rel="nofollow">http://www.pmchampion.com/</a></p>
]]></content:encoded>
	</item>
	<item>
		<title>By: admin</title>
		<link>http://www.pm-perspectives.com/project-time-management-key-tips-project-success/comment-page-1/#comment-3</link>
		<dc:creator>admin</dc:creator>
		<pubDate>Fri, 23 Jan 2009 00:05:47 +0000</pubDate>
		<guid isPermaLink="false">http://www.pm-perspectives.com/?p=35#comment-3</guid>
		<description>Ernest Gutierrez, PMP // May 1, 2008 at 6:05 pm 
Rosemary,
In our beloved Earned Value world, given 4 ways to calculate the Estimate At Completion Forecast:
EAC = AC + ETC
EAC = AC + BAC – EV
EAC = (AC + (BAC-EV)/CPI)
EAC = BAC / CPI (Not in PMBOK)
In what scenarios are each of the above calculations best used? Is there an order of optimistic to pessimistic? Thank you!

Ernest Gutierrez, PMP // May 1, 2008 at 6:05 pm</description>
		<content:encoded><![CDATA[<p>Ernest Gutierrez, PMP // May 1, 2008 at 6:05 pm<br />
Rosemary,<br />
In our beloved Earned Value world, given 4 ways to calculate the Estimate At Completion Forecast:<br />
EAC = AC + ETC<br />
EAC = AC + BAC – EV<br />
EAC = (AC + (BAC-EV)/CPI)<br />
EAC = BAC / CPI (Not in PMBOK)<br />
In what scenarios are each of the above calculations best used? Is there an order of optimistic to pessimistic? Thank you!</p>
<p>Ernest Gutierrez, PMP // May 1, 2008 at 6:05 pm</p>
]]></content:encoded>
	</item>
</channel>
</rss>

